The Commission on Audit said the Department of Public Works and Highways (DPWH) awarded 11,391 contracts worth P459.262 billion to firms with incomplete or inaccurate documents, which put into doubt their financial capacity to handle the projects.
The contracts were awarded from January 1, 2024 to August 31, 2025 by the DPWH Central Office and its regional offices.
The COA made the findings after studying 27,094 out of 47,469 infrastructure contracts.
According to the audit report on the DPWH, the 11,391 contracts involved parties that submitted incomplete reports about their ongoing projects.
This resulted in the incorrect computation of their Net Financial Contracting Capacity (NFCC), which is used to determine if a contractor is eligible to bid for a public works contract. It is computed based on a contractor’s assets, less its liabilities and financial commitments from ongoing projects.
The calculated NFCC must meet or exceed the Approved Budget for the Contract.
“Review of the 27,094 sampled infrastructure contracts disclosed that 11,391 contracts, with an aggregate contract cost of P459.262 billion, involved bidders whose submitted Statements of Ongoing Government and Private Contracts did not completely reflect their ongoing and awarded but not yet started contractual commitments,” the COA said.
The biggest contract costs that went to bidders with the doubtful NFCCs were in Region 4B or Mimaropa (P65.708 billion); Region 10 or Northern Mindanao (P63.559 billion); Region 1 or Ilocos Region (P45.76 billion); Region 2 or Cagayan Valley (P43.553 billion); and Region 4A or Calabarzon (P41.655 billion).
According to the COA, loopholes in the system were exploited to skew NFCC computations.
It said incomplete declarations were made about on-going and awarded but not yet started contracts, and the NFCC computations were not updated in the subsequent bid.
The contractors also did not disclose projects undertaken with other government agencies, local government units, government-owned or controlled corporations and private entities.
“(I)t was observed that bidders with undeclared ongoing and awarded but not yet started projects were still considered eligible, provided that they had a positive NFCC,” it said.
The COA cited examples to show how an inaccurate NFCC computation affects the awarding of contracts.
It showed the breakdowns of projects awarded to two bidders identified only as Contractor B and Contractor C in 2024.
Contractor B won a P144.75 million contract in January 2024. After this, its NFCC should have gone down from P226.34 million to P81.59 million.
But after winning the contract, it continued to bid for projects and won four more contracts in six days, with each contract higher than its remaining NFCC. The total project cost awarded to Contractor B was P675.5 million, which is way beyond its original NFCC.
A similar situation was seen in Contractor C, which won 7 contracts worth P1 billion in all despite having an NFCC of P189.75 million.
The contracts were awarded from January 30, 2024 to February 2, 2024 and ranged from P140.16 million to P144.75 million each.
“Considering the cumulative value of the succeeding contracts awarded to the same contractors, the remaining NFCC was no longer sufficient to satisfy the required financial eligibility for the subsequent awards,” the COA noted.
In response, the DPWH said the NFCC was checked for accuracy during the post-qualification stage to ensure compliance with the required contracting capacity. It also said the projects had not yet been awarded, so they were not considered in the computation of the NFCC.
It said the Bids and Awards Committee-Technical Working Group relied on the eligibility results generated by the DPWH Civil Works Application (CWA), which only contains data about DPWH-awarded contracts.
But it also acknowledged that it lacked an independent mechanism to cross-check contractors’ declared commitments against their actual ongoing government projects, even though this is a critical factor for assessing NFCC submissions.
It also said there had been time constraints for post-qualification and practical limitations that affect its independent verification of bidders’ submissions, such as the sheer volume of transactions and shortage in personnel.
But the DPWH management also assured the COA that all the Bids and Awards Committees, BAC Secretariats, and Technical Working Groups of the DPWH CO, ROs and district engineering offices would strengthen the NFCC validation during preliminary examination of bids and post-qualification.